4.
Insert two tool keepers (Figure 1, Item 2) in pavement breaker (Figure 1, Item 1).
5.
Insert tool keeper locking pin (Figure 1, Item 4) in pavement breaker (Figure 1, Item 1).
Figure 1. Pavement Breaker Tool Change
051
6.
After installing pavement breaker to machine (WP 0004), connect pavement breaker hoses to auxiliary connections (Fig-
ure 2, Item 1) on dipper (Figure 2, Item 2).
Figure 2. Pavement Breaker Hose Connection
051