NITROGEN RECHARGE
HYDRAULIC IMPACT BREAKER SET-UP AND OIL PRESSURE REGULATION

Technical Manual For Hydraulic Excavator Model 330Lcr 2
Page Navigation
  914    915    916    917    918  919  920    921    922    923    924  
img
TM 5-3805-281-24-2
Hydraulic Impact Breaker
33
4. Install inflating body to accumulator.
61
CED,OUOE039,4
1920MAR995/7
5. Using an Allen wrench (A), slowly unscrew square pin
on inflating body to open nitrogen.
6. To clean accumulator, set pressure regulator on tank
at its preset pressure value. Start nitrogen by opening
charging valve on tank, then close charging valve on
the tank and discharge nitrogen in accumulator shell.
7. Set pressure regulator on tank to value indicated in
Torque Specifications. Start nitrogen by opening
charging valve on tank. After about five minutes, when
pressure in accumulator has reached appropriate level,
close off square pin on inflating body with wrench.
8. Close nitrogen tank and discharge emissions pipe.
9. Attach pressure reducer/regulator once again to
inflating screw and check that pressure has reached
appropriate level (see Torque Specifications). Remove
regulator and tighten inflating screw with 14 mm Allen
wrench to final torque of 5 kg/m maximum.
Continued on next page
CED,OUOE039,4
1920MAR996/7
20-57