TM 5-3805-294-23-4
0622
INSTALLATION - Continued
15.
Lightly lubricate O-ring (Figure 2, Item 6) with clean oil.
16.
Install O-ring (Figure 2, Item 6) to line (Figure 2, Item 5).
17.
Install hose (Figure 2, Item 4) to line (Figure 2, Item 5).
18.
Lightly lubricate O-ring (Figure 2, Item 3) with clean oil.
19.
Install O-ring (Figure 2, Item 3) to line (Figure 2, Item 2).
20.
Install hose (Figure 2, Item 1) to line (Figure 2, Item 2).
END OF TASK
FOLLOW-ON MAINTENANCE
1.
2.
Perform the Standard Follow-On Maintenance Instructions. (Volume 3, WP 0384)
END OF TASK
END OF WORK PACKAGE