TM 5-3805-294-10
OPERATOR MAINTENANCE
TRACK SAG CHECK
INITIAL SETUP:
References (cont.)
Tools and Special Tools
Materials/Parts
Equipment Condition
Personnel Required
Horizontal Construction Engineer 12N (2)
Time to Complete
0.5 Hour(s)
References
RAISING MACHINE
NOTE
Sag for left and right side tracks is checked the same way.
1.
Swing upperstructure (Figure 1, Item 1) 90 degrees.
3
4
1
5
2
HYEX00383
Figure 1. Raise Machine.
2.
Place round side of bucket (Figure 1, Item 2) on ground.
3.
Keeping angle between boom (Figure 1, Item 3) and arm (Figure 1, Item 4) between 90 and 110 degrees,
slowly lower boom (Figure 1, Item 3) to raise track (Figure 1, Item 5) off ground.
END OF TASK