TM 5-3805-294-10
OPERATOR MAINTENANCE
CRUSH-ALL DISCHARGE MATERIAL SIZE ADJUSTMENT
INITIAL SETUP:
Tools and Special Tools
Equipment Condition
Wrench 2-1/4
Machine safely parked and shut down
Personnel Required
Time to Complete
Horizontal Construction Engineer 12N (1)
0.3 Hour(s)
References
DISCHARGE ADJUSTMENT
WARNING
Unless otherwise specified, perform all maintenance procedures with all attachments lowered
to the ground, pilot shutoff lever in the up position, and engine shut off. Failure to comply may
result in injury or death to personnel.
NOTE
Ensure curtain is set to desired discharge size before Crush-All operation.
There are no disassembly requirements to perform discharge adjustments. Adjustment
points are on the outside of the machine.
There are two adjustment points for lower curtain. Adjustment procedure is identical for
both points and must be adjusted at same time.
Raise curtain to increase discharge size.
Lower curtain to decrease discharge size.
To reduce dust, increase discharge size.
Repeat steps for opposite side.
1.
Loosen nut (Figure 1, Item 1) on nut (Figure 1, Item 2) and rod (Figure 1, Item 3).