TM 5-3805-294-10
OPERATOR MAINTENANCE
MAINTENANCE AFTER FORDING
INITIAL SETUP:
Tools and Special Tools
References
Materials/Parts
Equipment Condition
Machine safely parked and shut down.
Grease, Automotive and Artillery
Time to Complete
Personnel Required
Horizontal Construction Engineer 12N (1)
0.5 Hour(s)
DRAINING MUD OR WATER
1.
Remove two bolts (Figure 1, Item 1) and washers (Figure 1, Item 2) from cover (Figure 1, Item 3).
1, 2
3, 4
5
HYEX03286
Figure 1.
Draining Mud or Water.
2.
Remove cover (Figure 1, Item 3) and gasket (Figure 1, Item 4) from machine (Figure 1, Item 5) and allow mud
or water to completely drain.
3.
Remove any contaminated grease.
4.
Install cover (Figure 1, Item 3) and gasket (Figure 1, Item 4) to machine (Figure 1, Item 5) with two bolts (Figure
1, Item 1) and washers (Figure 1, Item 2).