TM 5-2420-230-24-1
b. Installation.
Steps in installation of muffler heat shield are the reverse of those in removal procedure.
c. Follow-On Maintenance.
END OF TASK
This Task Covers:
a. Removal
c. Inspection
d. Installation
b. Follow-On Maintenance
INITIAL SETUP
Test Equipment
Equipment Conditions
None
TM or Para
Condition Description
Muffler heat shield removed.
Tools and Special Tools
Drawings Required
Materials/Parts
Estimated Time to Complete
Personnel Required
MOS 62B, Construction Equipment Repairer
References
None
a. Removal.
Hot parts can burn personnel. Let hot parts cool before starting work.
(1)
Remove mounting bolts securing top and bottom of muffler.
(2)
Loosen clamp securing muffler to exhaust pipe.
(3)
Remove muffler.