TM 5-3805-294-10
0019
INSTALLING CRUSH-ALL - Continued
7
HYEX03393
Figure 5. Quick Latch Switch to Latch Position.
14.
Raise boom (Figure 6, Item 12) to allow adequate ground clearance of crush-all (Figure 6, Item 11).
12
14
13
8
9
11
HYEX03395
Figure 6.
Position Crush-All.
15.
Curl crush-all (Figure 6, Item 11) as in Figure 6 until quick latch wedges (Figure 6, Item 9) are fully engaged
to crush-all (Figure 6, Item 11).
16.
Rotate safety lock pin lever (Figure 6, Item 13) to lock position.
17.
Extend arm cylinder (Figure 6, Item 14) and lower boom (Figure 6, Item 12) to position crush-all (Figure 6, Item
11) on ground.
18.
19.
Clean cap (Figure 7, Item 15) and machine quick disconnect (Figure 7, Item 16) with rag.