Prior to commencement of maintenance on the Interim High-Mobility Engineer Excavator (IHMEE), perform the following
procedure:
(1)
Ensure vehicle is positioned on level ground.
(2)
(3)
Raise FEL, install maintenance arm, and lower FEL onto maintenance arm, as required (TM 5-2420-230-10).
(4)
(5)
(6)
Upon completion of maintenance activities, restore power and return vehicle to operational readiness using the following
procedure:
(1)
(2)
(3)
(4)
(5)
Raise FEL, remove maintenance arm, and lower FEL to ground or travel position as required
(6)
Complete necessary documents and return IHMEE to relevant authority.
This Task Covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Test Equipment
Equipment Conditions
None
TM or Para
Condition Description
Vehicle positioned on level
ground.
Tools and Special Tools
Parking brake applied.
Engine shut OFF.
Electrical master switch OFF.
Materials/Parts
"Do Not Operate" tag attached
to ignition switch.
Personnel Required
Drawings Required
MOS 62B, Construction Equipment Repairer
References
Estimated Time to Complete Task
None