b. Installation.
NOTE
Ensure all hoses are reconnected to positions noted prior to removal.
Install cable ties as necessary.
Ensure hoses are clean and contain no foreign matter.
(1)
Install elbow (8), if necessary.
(2)
Install new gasket (7) on air compressor (3).
(3)
Install air compressor (3) with two washers (5) and nuts (4) on engine studs (6). Torque nuts to 57 lbf/ft (77 Nm).
(4)
Install oil supply line (2) at bottom of air compressor (3).
(5)
Install air supply line (1).
c. Follow-On Maintenance.
(1)
(2)
(3)
(4)
END OF TASK
This Task Covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Test Equipment
References
None
None
Special Tools
Equipment Condition
TM or Para
Condition Description
Air system drained.
Left front belly plate removed.
Materials/Supplies
Drawings Required
Personnel Required
Estimated Time to Complete Task
MOS 62B, Construction Equipment Repairer