TM 5-2420-230-24-1
Upon completion of maintenance activities, restore power and return vehicle to operational readiness using the following
procedure:
(1)
(2)
(3)
(4)
(5)
Raise FEL, remove maintenance arm, and lower FEL to ground or travel position as required
(6)
Complete necessary documents and return IHMEE to relevant authority.
This Task Covers:
a. Removal
b. Disassembly
c. Assembly
d. Installation
e. Follow-On Maintenance
INITIAL SETUP
Test Equipment
References
None
None
Tools and Special Tools
Equipment Conditions
TM or Para
Condition Description
Stabilizer lowered.
Hydraulic system pressure
Equipment, suitable lifting
released.
Materials/Parts
Drawings Required
Grease, automotive and artillery, Item 30, Appendix C
Estimated Time to Complete Task
Personnel Required
MOS 62B, Construction Equipment Repairer (2)
Change 1