This Task Covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Test Equipment
Equipment Conditions
None
TM or Para
Condition Description
Joystick removed.
Rocker switches removed.
Tools and Special Tools
Main hydraulic master switch
removed.
Indicator lights removed.
Materials/Parts
None
Drawings Required
Personnel Required
MOS 62B, Construction Equipment Repairer
Estimated Time to Complete Task
References
None
a. Removal.
(1)
Remove four screws (1) from hand control pod
assembly (2).
(2)
Remove hand control pod assembly (2) from
arm rest (3).
b. Installation.
Install hand control pod assembly (2) to arm rest (3)
with four screws (1).
c. Follow-On Maintenance.
(1)
(2)
Install main hydraulic master switch
(3)
(4)
(5)
(6)
END OF TASK