TM 5-2420-230-24-1
This Task Covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Test Equipment
References
None
None
Tools and Special Tools
Equipment Conditions
TM or Para
Condition Description
Arctic heater removed.
Materials/Parts
Drawings Required
Personnel Required
Estimated Time to Complete Task
MOS 62B, Construction Equipment Repairer
a. Removal.
NOTE
Tag all wires and note their positions before
removal.
(1)
Remove two screws (1), screw (2),
screw (3), control unit (4) and grommet (5)
from arctic heater (6).
(2)
Unplug connector (7).
b. Installation
NOTE
Ensure all wires are reconnected to positions
noted prior to removal.
(1)
Plug in connector (7).
(2)
Position grommet (5) on control unit (4).
(3)
Install control unit (4) on arctic heater (6)
with screw (3), screw (2), and two
screws (1).
c. Follow-On Maintenance.
END OF TASK
Change 1